On most of the homes in a stretch of northern Desert Hot Springs, "septic" on a listing describes a stage. Mission Springs Water District plans to connect about 695 properties in its Area M-2 to the public sewer system and retire roughly 405 older septic tanks. The district has funding in hand for only part of that area. It has published a construction schedule running into late summer 2027. So two listings a few blocks apart can say the same thing and be in very different positions. One may be scheduled for a grant-funded conversion within months. The other may be waiting on a state decision that hasn't been made yet.
Comparing homes here means asking where a property sits in that sequence, along with the usual question of whether it's on septic.
MSWD describes the M-2 project area as northern Desert Hot Springs plus some surrounding unincorporated Riverside County. It is roughly bounded by San Gorgonio Street on the north, Dillon Road on the south, Yerxa Road on the east, and Avenida Gracia on the west. On the district's map, M-2 is labeled Assessment District 15, separate from the earlier AD-12 areas M-1 and L-1.
The reason behind the project is older than the project. In March 2004, the Colorado River Basin Regional Water Quality Control Board adopted a resolution that prohibits waste discharge from existing or new septic systems on parcels under one-half acre over the Mission Creek or Desert Hot Springs aquifers, once a sewer system is available. The resolution says these aquifers are vulnerable to septic contamination because of how densely septic systems sit in the area's permeable soils. It lists nitrate, pathogens, and dissolved solids among the risks. MSWD estimates that M-2 will keep about 37 million gallons of wastewater a year out of the local groundwater basin.
For a buyer, the trigger in that 2004 language matters most. The rule applies when sewer becomes available. On a small lot over these aquifers, a septic system's future depends on when the sewer main reaches the street. The age or condition of the tank matters less.
MSWD presented a construction schedule at a homeowner workshop on July 23, 2026. The district marks it as subject to change. As published, it looks like this:
Phase | Streets named | Sewer work | Septic abatement | Water line work | Roadwork |
|---|---|---|---|---|---|
Phase 2 | Carlos St, Camino Silvoso, Bubbling Well Rd | Aug 19 to Oct 28, 2026 | Oct 8 to Oct 28, 2026 | Oct 6 to Nov 10, 2026 | Nov 23 to Dec 22, 2026 |
Phase 4 | San Jacinto, San Antonio, San Tomas, San Andreas, San Gorgonio streets | Nov 30, 2026 to Mar 19, 2027 | Apr 19 to June 10, 2027 | Apr 5 to June 7, 2027 | Aug 6 to Aug 26, 2027 |
Phase 1 | Bubbling Wells School vicinity | Two windows, starting Dec 21, 2026 and Mar 22, 2027 | Mar 22 to Apr 16, 2027 | June 7 to Aug 5, 2027 | July 23 to Aug 5, 2027 |
As of early October 2026, that schedule puts Phase 2 in its busiest weeks. Septic abatement and water line work are both set to start this month. A home on Camino Silvoso and a home on San Tomas Street might show the same septic notation today. On the published plan, though, their tanks are scheduled to close about eight months apart.
Two cautions apply. First, the district's materials forecast an August 2026 construction start, but none of the sources we reviewed confirm that crews have broken ground. Second, the schedule's first date range for Phase 1 sewer work has a printing error, with an end date earlier than its start. Treat those dates as approximate until MSWD reissues them. MSWD says residents will get advance notice before work begins near their property. Those notices are the most reliable signal for any particular street.
The district's September 17, 2026 board agenda shows the project moving forward administratively. It included a second contract amendment, for $1,429,387, to Willdan Engineering for construction management on the AD-15 Area M-2 sewer and water line replacement project. The same agenda recommended accepting the separate Regional Sewer Conveyance Line Project as complete. That is part of the regional system M-2 will feed into.
The schedule only covers part of the area. MSWD says current funding covers the first 298 properties, split into three phases. The remaining phases depend on a funding amendment from the State, which the district expects in winter 2026 or spring 2027. That leaves roughly 397 of the area's 695 properties outside the money currently committed.
For funded properties, the terms are generous. MSWD secured $68 million from the State Water Resources Control Board for the Nancy Wright Regional Water Reclamation Facility, the Regional Conveyance Line Project, and the M-2 work. The workshop slides list $0 in direct construction cost to participating owners. The project covers sewer mains, manholes, and public service laterals, along with connection, septic tank abandonment, and street restoration. The FAQ says the grant pays for construction, abatement, and connection costs "which would typically be paid by the homeowner." Abatement means pumping the old tank, crushing it, and filling it under County and District requirements. MSWD and its contractor handle the permits and final inspection.
For properties outside the funded group, the published material doesn't say. It gives no cost figure for an owner whose parcel is in a later phase if the state amendment arrives late or comes in smaller than requested. It also gives no parcel-by-parcel list showing which addresses are in the funded 298. The July schedule names Phases 1, 2, and 4 but doesn't explain how those numbers line up with the three funded phases. Until MSWD publishes that detail, the only way to know a specific parcel's status is to ask the district directly. Its FAQ points owners to MSWD.org/M2 and the Public Affairs team.
A grant-funded conversion still comes with ongoing costs. Once a property is connected, MSWD says the owner should plan for a monthly sewer service fee. It goes on the water bill until the start of the next fiscal year. After that, the owner can prepay it annually or have it placed on the property tax bill. The FAQ lists the current sewer service rate as $53.75. In April 2026, MSWD's board adopted Resolution 2026-02, setting up collection of fiscal 2026–27 sewer user fees on the county tax roll.
This shows up in a buyer's monthly costs. A septic home has no sewer bill, only periodic pumping and the risk of a failure. A connected home has a recurring charge that may appear on the property tax bill instead of the utility bill. When you compare two homes in M-2, look at the tax bill as well as the water bill.
The paired water project changes something more physical. MSWD is replacing aging water lines and meters that now sit in hard-to-reach rear-yard easements, and doing it at the same time as the sewer work so streets are only opened once. For an owner, a meter in the backyard easement means crews need access through the yard. Moving it improves access for both MSWD and the homeowner. MSWD says its contractors will generally leave properties as they found them and will try to restore any landscaping the work disturbs. If you're buying a home with a finished backyard in Phase 4 or Phase 1, assume some of the yard may be disturbed and repaired after closing.
Riverside County's environmental health page covers septic permits for installation, repair, and modification. It doesn't describe a septic inspection requirement at sale. We also found nothing showing that the M-2 project itself triggers a disclosure or payment at transfer. That puts the job of asking on the buyer. A useful order:
Sellers can answer most of these before listing. A folder with MSWD correspondence, the parcel's phase, and copies of submitted forms turns a buyer's open question into a known schedule.
Does a funded M-2 owner pay to connect? Under the grant agreement as MSWD describes it, the State covers construction, septic abatement, and connection costs for funded properties. The owner then pays a monthly sewer service fee.
Will I be able to get to my home during construction? MSWD says access will be maintained, with possible temporary changes to lanes or driveways near active work. Streets are to be repaved afterward.
Is there a deadline to hook up? The FAQ gives no individual hookup deadline. MSWD's broader timeline shows connections and septic abatement continuing into 2027 and beyond.
I rent in the project area. How will I find out? MSWD encourages owners to pass project notices along to tenants. Contractors will also leave door hangers when work will affect access or happen nearby.
If you're looking at a home between San Gorgonio Street and Dillon Road, or getting ready to sell one, Catherine Joubert can help you sort out where the property stands in the M-2 sequence and what to ask MSWD before you commit. Let's Connect.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.
Stay up to date on the latest real estate trends.
Catherine delivers top-tier real estate service, treating all clients like celebrities. Whether you seek a condo in Palm Desert, a golf course property in La Quinta, or a mid-century modern home in Palm Springs, she provides expert guidance for a seamless experience. Get in touch with Catherine today to discuss your next steps.